» Wisconsin has long been a national leader in dam building. The world’s first hydropower project was completed here on the Fox River in 1882. While, the state officially counts more than 3,800 dams, the actual total including unregulated and abandoned dams is closer to 10,000. It is fitting then that Wisconsin is becoming a leader in dam removal.
In 1929, the Wisconsin Lutheran Seminary built a 24-foot timber and stone dam to create a pond on their 80-acre campus in Mequon, Wisconsin. In the 1950s the dam was rebuilt of concrete that, by 2000, had badly degraded. The dam wall leaned downstream and falling concrete exposed steel rebar beneath. Dredging of built-up sediment was long overdue and in the summer the pond was choked with algae and attracted nuisance Canada geese.
When the downstream Village of Thiensville began studying flood control in the Pigeon Creek watershed, their engineering consultants recommended removal of the dam. In spring 2006, Milwaukee Riverkeeper and Will Wawryzn from the state Department of Natural Resources met with the Seminary to present a plan for removal of the dam. Repairing the dam would cost more than $100,000, plus additional funds to dredge sediment from the pond. Removal, however, was estimated to cost $38,000, which the state would pay with funds from an environmental damage compensation fund. Repairing dams generally costs three to four times more than removing them. To their credit, the Seminary responded very positively not only to the economics, but to the ecological benefits of removing the dam.
Although we were worried about possible opposition to removing the pond, most public reaction was very positive. But there were obstacles. For example, the dam breach was pushed back almost a year so the Seminary could install fire hydrants. The fire department had relied on the pond as a water supply for firefighting.
Despite its small size, removing the Seminary Dam had a significant ecological impact — opening up 25 miles of stream and more than 600 acres of wetlands to migrating Steelhead, Salmon, Northern Pike, Sturgeon and Walleye.
The dam was slowly breached in spring 2007 and water quality downstream of the dam quickly rebounded. In fall 2008, state officials doing fish surveys witnessed Chinook Salmon and Steelhead Trout adults, fish that had likely made the 23 mile migration from Lake Michigan. They also witnessed Steelhead or Rainbow Trout smolts, juvenile fish, which likely spawned in the creek the previous spring. Riverkeeper is completing more intensive surveys with the goal of formally re-classifying the creek as a trout stream. In addition, Smallmouth and Largemouth bass have returned to the creek. We are hopeful other native fishes, such as the marsh spawning Northern Pike and Walleye, will return.
Riverkeeper and our volunteers will continue our in-stream work, restoring the meandering flow of the creek, stabilizing the new stream banks and replanting native vegetation. Milwaukee Riverkeeper will conduct water monitoring to document the return of Pigeon Creek. The Seminary has announced plans to upgrade trails adjacent to the restored creek and improve access for fishing.
|
Fish populations rebounded quickly after the removal of the Seminary Dam.
Milwaukee Riverkeeper
|